The Giant Magellan Telescope joins seven 8.4-meter mirrors into one 25.4-meter telescope, with construction waiting on NSF
The Giant Magellan Telescope (GMT) is a 25 m class optical and infrared telescope: seven 8.4 m primary mirrors and seven 1 m deformable secondary mirrors, for an aperture of 25.4 m and a collecting area of 368 square meters. GMTO says its images will be 10 times sharper than Hubble's. Its science aims include finding habitable exoplanets.
GMTO Corporation, a nonprofit, builds it for a consortium of 15 institutions in the US, Australia, Brazil, Chile, Israel, South Korea and Taiwan (end of 2024); MIT joined in September 2025. Daniel T. Jaffe of UT Austin became president on 13 January 2026, and Taft Armandroff chairs the board. Partners have put in more than $1 billion, mostly from donors. The total to build and operate was about $2.54 billion in a 2024 estimate and over $2 billion in an April 2026 report.
The GMT entered the NSF Major Facilities Final Design Phase in June 2025 and is the one US Extremely Large Telescope Program project at that stage; NSF capped its giant-telescope budget at $1.6 billion in 2024. The FY2026 spending report of January 2026 told NSF to move both the GMT and the Thirty Meter Telescope to final design review. The NSF FY2027 request has no design funds, because GMTO said it can finish final design without new NSF money. The sources disagree on when the final design review falls: June 2026, mid-2027 or late 2027. In April 2026 about 40% of the components were in fabrication and assembly; full construction would start in FY2028 if NSF and Congress fund it, for science in the 2030s.
The site is Las Campanas Observatory in the Atacama Desert of Chile, at 2,516 m, owned by the Carnegie Institution for Science since 1960 and already home to the twin 6.5 m Magellan Telescopes. The telescope was moved slightly before excavation after wind modeling, and its foundations are dug. See the Giant Magellan Telescope listing, the largest optical telescopes and more observatories in Chile.
Advertisement
The Arizona Mirror Lab has cast all seven primary mirrors from Japanese glass, and three are finished
The Richard F. Caris Mirror Lab at the University of Arizona casts and polishes the primaries. Each mirror is 8.417 m across and weighs 17 t. The glass is Ohara E6 low-expansion borosilicate, melted in Japan; the Mirror Lab bought 20 t of it for the seventh segment. A GMTO caption from December 2024 calls the melt site the Chiba Kogaku glass factory, and no source found ties that name to Ohara.
The first mirror was cast in November 2005 and the seventh in October 2023, with an eighth planned as a spare. GMTO's latest count, from its 2024 status paper, is three mirrors complete, two in storage and one in optical testing, and four in fabrication; neither GMTO nor the Mirror Lab has published a 2026 count. In October 2024 a finished mirror went into the prototype test cell of its support system.
Each mirror floats on a pneumatic support of about 160 actuators, about 200 actuators and sensors in all. The instrumentation lab at Texas A&M University assembled and tested 160 prototype actuators from 2019 to 2021; production starts in 2027, and the production supplier is not publicly named. OHB Italia finished the first of seven mirror covers in April 2023.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| Seven 8.4 m primary mirrors, casting and polishing | Richard F. Caris Mirror Lab, University of Arizona | US | Manufacturer | In production | All seven cast (seventh Oct 2023); three complete and four in fabrication per GMTO SPIE 2024 status paper; no 2026 count published |
| E6 borosilicate glass for primary mirror casting | Ohara Corporation | Japan | Manufacturer | Delivered | Ohara lists GMT among E6 customers; Mirror Lab team bought 20 t of Ohara E6 for segment seven; melted in Japan |
| Primary mirror pneumatic support actuators, 160 assembled and tested | Texas A&M University instrumentation lab | US | Manufacturer | Delivered | Prototype set for the test cell, 2019 to 2021; production actuator supplier not public |
| Mirror covers, first of seven | OHB Italia S.p.A. | Italy | Manufacturer | Delivered | First unit finished April 2023 |
Seven adaptive secondary mirrors, 2 millimeters thick, carry 4,725 actuators between them
The GMT corrects the atmosphere at its secondary mirror. Each of the seven adaptive secondary mirror (ASM) segments is a thin Zerodur shell about 1 m across and 2 mm thick, pushed by 675 voice coil actuators, 4,725 in all. AdOptica, the Italian partnership of A.D.S. International and Microgate, builds this fourth-generation ASM. SCHOTT supplied the Zerodur blank and Safran Reosc ground and polished the off-axis shell under a July 2021 contract, with about 10 times the asphericity of its earlier shells. KRISS in South Korea co-produced the reference body with the University of Arizona, and A.D.S. built the prototype hexapod positioner. Two off-axis face sheets arrived in May 2025.
Phasing without edge sensors
Seven separate mirrors must be phased to a fraction of a wavelength, and the GMT does it optically rather than with edge sensors. The acquisition, guiding and wavefront sensing system (AGWS) and the natural guide star wavefront sensor (NGWS), tested with INAF Arcetri, are joined by a holographic dispersed fringe sensor; the Smithsonian Astrophysical Observatory built a dispersed fringe sensor prototype and demonstrated closed-loop phasing. Assembly of the GAPS phasing testbed began in Pasadena in December 2025. The makers of the real-time adaptive optics computers are not publicly named.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| Adaptive secondary mirror (ASM) system, seven segments | AdOptica (A.D.S. International and Microgate) | Italy | Integrator | In production | Fourth-generation ASM; 675 voice coil actuators per segment, 4,725 total; Safran Reosc shell and SCHOTT blank under AdOptica; segment assembly ready for Phasing Testbed by Dec 2025 |
| ASM design (AdOptica member) | Microgate | Italy | Designer | In production | AdOptica member; contactless voice coil technology; 675 actuators per segment, 4,725 total |
| ASM prototype hexapod positioner actuator | A.D.S. International | Italy | Manufacturer | Delivered | Also received the first off-axis thin shell in 2024 |
| ASM off-axis thin shell, 1 m class, 2 mm thick, ground and polished | Safran Reosc | France | Manufacturer | Delivered | Contract July 2021 under AdOptica; asphericity about 10 times its prior shells |
| Zerodur blank for ASM thin shell | SCHOTT AG | Germany | Manufacturer | Delivered | Named in GMT SPIE 2024 status paper |
| ASM reference body, co-producer | Korea Research Institute of Standards and Science (KRISS) | South Korea | Manufacturer | Delivered | Co-produced with University of Arizona |
| Natural guide star wavefront sensor prototype testing | INAF Arcetri | Italy | Designer | In production | Tested in the HCAT testbed at University of Arizona |
| Dispersed fringe sensor prototype and closed-loop phasing demonstration | Smithsonian Astrophysical Observatory | US | Designer | Delivered | Segment phasing; GMT has no published edge-sensor supplier |
Ingersoll is building the 2,100-metric-ton mount in Illinois, and the enclosure still has no builder
The mount stands 39 m tall on a 22 m concrete pier and weighs 2,100 t with its optics. OHB Digital Connect of Germany, formerly MT Mechatronics, designed it, and Ingersoll Machine Tools, part of Italy's Camozzi Group, builds and tests it in Rockford, Illinois, under a $135 million contract signed in October 2019. Fabrication began in August 2024 and runs about six years; the 2019 plan had the mount in Chile by the end of 2025. Teledyne in Huntsville, Alabama rough-machines the azimuth track sections and Dynasty Fab near Detroit makes the azimuth disk sections.
The enclosure is about 65 m tall, 60 m wide and 4,800 t, with 92 wind vents and 24 seismic pendulums that let it move 700 mm in an earthquake. It turns a full circle in about four minutes by one account and a little over three by another. M3 Engineering of Tucson was named as its designer in 2019; IDOM of Spain won the final design in March 2022, passed the final design review in June 2024, and is Designer of Record. Boeing and RWDI modeled the wind loads. WSP has been construction manager since January 2018. In October 2026 GMTO was preparing to select a contractor, and the enclosure construction contractor is not publicly named.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| Telescope mount design, 39 m tall, 2,100 t with optics | OHB Digital Connect (formerly MT Mechatronics) | Germany | Designer | Delivered | Contract Oct 2019, USD 135 million with Ingersoll |
| Telescope mount manufacture, assembly and factory test | Ingersoll Machine Tools (Camozzi Group) | US | Manufacturer | In production | Fabrication began Aug 2024 in Rockford IL; about six years of work |
| Azimuth track sections, rough machining | Teledyne (Huntsville AL) | US | Manufacturer | In production | Named in GMT SPIE 2024 status paper |
| Azimuth disk sections | Dynasty Fab | US | Manufacturer | In production | Near Detroit MI |
| Enclosure final design, 65 m tall, 4,800 t | IDOM | Spain | Designer | Delivered | Designer of Record; final design review passed June 2024; no construction contractor named as of Nov 2026 (GMTO preparing contractor selection Oct 2026) |
| Earlier enclosure design | M3 Engineering | US | Designer | Delivered | Tucson firm named in 2019 as having designed the enclosure |
| Wind loading fluid dynamics modeling | Boeing | US | Designer | Delivered | With RWDI |
| Wind loading fluid dynamics modeling | RWDI | Canada | Designer | Delivered | With Boeing |
| Construction manager | WSP | Canada | Integrator | Contracted | Awarded January 2018 |
G-CLEF, GMACS and GMTNIRS will be the first instruments
G-CLEF, an optical echelle spectrograph from the Center for Astrophysics, Harvard and Smithsonian, is in fabrication; its vacuum chamber was nearly complete in December 2025. GMACS, a visible multi-object spectrograph from the CfA with the Steiner Institute in Sao Paulo, is in final design and will be the second instrument commissioned. GMTNIRS, a near-infrared spectrograph from UT Austin and the Korea Astronomy and Space Science Institute (KASI), will be the first diffraction-limited instrument; its gratings and first cameras were delivered by December 2025. GMagAO-X and GMTIFS are in final design and MANIFEST is near the end of conceptual design. GMTO's 2024 status paper names no detector supplier.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| G-CLEF optical echelle spectrograph | Center for Astrophysics, Harvard and Smithsonian | US | Designer | In production | Vacuum chamber nearing completion Dec 2025 |
| GMTNIRS near-infrared spectrograph | University of Texas at Austin | US | Designer | In production | With KASI; gratings and first cameras delivered by Dec 2025 |
| GMTNIRS near-infrared spectrograph | Korea Astronomy and Space Science Institute (KASI) | South Korea | Designer | In production | With UT Austin |
| GMACS visible multi-object spectrograph | Center for Astrophysics, Harvard and Smithsonian | US | Designer | Planned | In final design as of June 2024; with Steiner Institute, Sao Paulo |
NOIRLab will write the software astronomers use to request GMT observations
NSF NOIRLab is to provide the observatory software that external astronomers use to request and define observations, and GMTO manages its requirements in IBM DOORS. The Operations Plan passed external review in October 2025. The real-time computers, the data center and any AI or machine-learning program are not publicly named.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| Observatory software for observation requests | NSF NOIRLab | US | Designer | Planned | Named in 2022 status paper |
| Requirements management tool (DOORS) | IBM | US | Manufacturer | In service | Manages GMT requirements |
Las Campanas runs daytime tours, but whether they include the GMT site is not stated
Las Campanas Observatory offers daytime tours booked through its visit site, a form for arranging visits and a virtual night tour. Its pages do not say whether tours include the GMT site, or give fees and hours.
Sources
- Space.com: the Giant Magellan Telescope and its funding
- Wikipedia: Giant Magellan Telescope
- ENR: building the Giant Magellan Telescope
- Las Campanas Observatory
- GMTO: 2024 in review
- GMTO: 2025 in review
- Texas takes charge of the Giant Magellan Telescope
- NSF: FY 2027 budget request to Congress
- AAS: NASA and NSF updates at AAS 248
- optics.org: a GMT mirror in its support test cell
- Texas A&M: GMT mirror actuators
- GMTO: adaptive secondary mirror final design
- GMTO: mount fabrication begins
- GMTO: telescope mount contract
- GMTO: project status, SPIE 2024
- GMTO: news
- Ohara: E6 borosilicate glass
- University of Arizona: casting the seventh GMT mirror
- GMTO: project status, SPIE 2022
- University of Arizona: a massive mount for giant mirrors
- Safran: first off-axis ASM shell for the GMT