The ELT will be the largest optical telescope ever built, with first light set for March 2029
ESO's Extremely Large Telescope (ELT) is a 39 m segmented telescope for optical and infrared light, from the visible to the mid-infrared, with a collecting area of 978 square meters. Its concave primary mirror, M1, is the largest optical primary ever made. The science goals are direct images of exoplanets and their atmospheres, the formation of stars and galaxies, and tests of dark matter and dark energy.
The European Southern Observatory (ESO), the intergovernmental organization that runs all its observatories in Chile, builds and will operate the ELT. ESO Council approved it in June 2012 and gave the construction green light in December 2014, at about EUR 1 billion for the first phase; with first-generation instruments the 2017 figure was EUR 1.15 billion. In December 2025 the Cost to Complete rose by almost EUR 90 million, which ESO absorbs into a very tight long-term budget. One report puts telescope and instruments together at about EUR 2.6 billion; the sources disagree on the total.
In March 2025 ESO moved the schedule: telescope first light in March 2029 and the first observations with scientific instruments in December 2030. ESO named contract delays, harsh weather, slower technology development and failures of manufacturing equipment as the causes, and the Director General confirmed the dates in December 2025. In July 2026 the project was more than 75% complete, and in mid-2026 the main structure turned on its vertical axis for the first time.
The telescope stands on Cerro Armazones in the Atacama Desert, at 3,046 m, about 20 km from ESO's Paranal Observatory. Chile and ESO signed a land agreement for 189 square kilometers around the mountain in October 2011, the land was donated in October 2013, and the summit was partly flattened in June 2014. See the Extremely Large Telescope listing, the largest optical telescopes and more observatories in Chile.
Advertisement
798 hexagonal segments, each held to about 2 nanometers, make the 39-meter primary mirror
The ELT folds its light through five mirrors. M1 is 798 hexagonal segments, each about 1.45 m across, about 5 cm thick and about 250 kg with its support, with 4 mm gaps between them. ESO ordered 931 segments: the extra 133 are a seventh sector of spares, so that two segments a day can come out for recoating and every segment is recoated every 18 months. Each segment is polished to surface errors no greater than about 8 nm, and all of them must stay aligned to about 2 nm to act as one surface. A further 18 spare blanks, for 949 in all, appear in one report; ESO counts 931.
SCHOTT casts the Zerodur glass-ceramic blanks in Mainz, the first in January 2018, for M1 and for M2, M3 and the M4 shells. Safran Reosc polishes, tests and integrates the M1 segments in a EUR 30 million, 5,000 square meter building in Poitiers, and said on 6 October 2026 that all 931 will be finished by the end of 2026. It polishes M2 to M5 at Saint-Pierre-du-Perray.
M2 is 4.25 m across and 3,533 kg, and M3 is 4.0 m and 3,258 kg, both Zerodur; each mirror with its cell weighs about 12 t. ESO's timeline page gives M3 as 3.75 m. SENER of Spain built the M2, M3 and M5 cells and the manipulator that handles M1 segment assemblies. M5, a flat elliptical tip-tilt mirror about 2.7 m by 2.2 m, is six brazed segments of silicon carbide from Mersen Boostec of France, polished by Safran Reosc. A separate commissioning M5 uses a SCHOTT blank polished by Glyndwr Innovations in the UK.
Supports, actuators and edge sensors: about 2,500 actuators and 9,000 sensors under M1
TNO of the Netherlands designed and prototyped the 27-point whiffletree that carries each segment, CESA of Spain built design and qualification units, and VDL ETG Projects made the series supports. Physik Instrumente (PI) of Germany supplied about 2,500 PACT position actuators, three per segment, with 2 nm accuracy over a 10 mm stroke; nine warping harness actuators per segment correct its shape. The FAMES consortium of Fogale (France) and Micro-Epsilon (Germany) made about 9,000 edge sensors, 4,500 pairs, that measure piston, gap and shear between neighbors. IDOM of Spain led the M1 Local Coherencer, the interferometer that phases the segments, with optics from UPC CD6 in Barcelona; it reached ESO in Munich for validation in May 2026. PROCON of Germany integrated the M1 local control cabinets, with heat exchangers from AAVID Thermalloy.
Coating: segments recoated on site
AGC of Belgium designed and built the coating plants for the M1 segments, and Fagerstrom Industrikonsult of Sweden the plant that washes and strips the old coating.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| M1 segment blanks in Zerodur (931 segments incl. spares) | SCHOTT AG | Germany | Manufacturer | Delivered | First blanks cast Jan 2018 in Mainz; ESO contract May 2017 to Sep 2022 marked completed |
| M1 segment polishing, testing and integration with supports | Safran Reosc | France | Manufacturer | In production | Poitiers plant; Safran release of 6 Oct 2026 says all 931 segments completed by end of 2026 (release did not load; content per reports quoting it) |
| M2 secondary mirror blank, 4.25 m Zerodur | SCHOTT AG | Germany | Manufacturer | Delivered | ESO contract Jan 2017 to Jan 2019 marked completed |
| M2 secondary mirror figuring and polishing | Safran Reosc | France | Manufacturer | Delivered | ESO timeline lists M2 complete in 2026; Saint-Pierre-du-Perray site |
| M3 tertiary mirror blank in Zerodur | SCHOTT AG | Germany | Manufacturer | Delivered | ESO contract Jan 2017 to Jul 2019 marked completed |
| M3 tertiary mirror figuring and polishing | Safran Reosc | France | Manufacturer | In production | ESO timeline plans M3 complete in 2027 |
| M5 flat tip-tilt mirror, lightweight silicon carbide substrate | Mersen Boostec | France | Manufacturer | Contracted | Six brazed SiC segments made to Safran Reosc specifications |
| M5 mirror blank and polishing | Safran Reosc | France | Manufacturer | In production | ESO timeline plans M5 complete in 2028 |
| M5 commissioning mirror blank | SCHOTT AG | Germany | Manufacturer | Delivered | ESO contract Mar 2024 to Oct 2024 |
| M5 commissioning mirror polishing | Glyndwr Innovations | UK | Manufacturer | In production | ESO contract Jun 2024 to Dec 2027 |
| M2 and M3 mirror cells | SENER | Spain | Manufacturer | Delivered | Each mirror plus cell about 12 t |
| M5 cell and tip-tilt unit with control system | SENER | Spain | Manufacturer | Delivered | ESO contract Nov 2019 to Mar 2024 |
| M1 segment support units, series production | VDL ETG Projects | Netherlands | Manufacturer | Delivered | 27-point whiffletree per segment; contract Apr 2018 to May 2022 |
| M1 segment support design and prototypes | TNO | Netherlands | Designer | Delivered | Designed and prototyped the supports |
| M1 segment support design and qualification units | CESA | Spain | Designer | Delivered | ESO contract Feb 2015 to Oct 2017 marked completed |
| Manipulator for M1 segment assemblies | SENER | Spain | Manufacturer | Delivered | ESO contract Jan 2021 to Feb 2024 |
| M1 Local Coherencer, segment piston and tilt interferometer | IDOM | Spain | Integrator | Delivered | Led development; delivered to ESO Munich May 2026 for validation |
| M1 Local Coherencer optical system | UPC CD6 (Universitat Politecnica de Catalunya) | Spain | Manufacturer | Delivered | Under 300 nm accuracy over a 250 micron range |
| M1 edge sensors, about 9,000 (4,500 pairs) | Fogale (FAMES consortium) | France | Manufacturer | Delivered | FAMES contract Jan 2017 to May 2022 |
| M1 edge sensors (FAMES consortium) | Micro-Epsilon (FAMES consortium) | Germany | Manufacturer | Delivered | Partner with Fogale |
| M1 position actuators (PACT), about 2,500 | Physik Instrumente (PI) | Germany | Manufacturer | Delivered | Three per segment; 2 nm accuracy, 10 mm stroke |
| M1 local control system cabinets, procurement and AIV | PROCON | Germany | Integrator | Delivered | ESO contract Dec 2020 to Jul 2022 marked completed |
| Heat exchangers for M1 local control system cabinets | AAVID Thermalloy | US | Manufacturer | Delivered | ESO contract Nov 2020 to Dec 2021 marked completed |
| M1 mirror coating plants, design and manufacture | AGC | Belgium | Manufacturer | Delivered | Contract Jun 2018 to Dec 2021; second contract for a large-mirror coating plant May 2021 to Feb 2024 |
| M1 washing and stripping plant | Fagerstrom Industrikonsult AB | Sweden | Manufacturer | Delivered | Design, manufacture, transport, on-site assembly and verification |
M4 reshapes its 2.4-meter surface up to 1,000 times a second with more than 5,000 actuators
The ELT builds adaptive optics into the telescope itself. M4 is a flat adaptive mirror 2.4 m across, made of six petals of glass-ceramic only 1.95 mm thick. More than 5,000 voice coil actuators reshape it up to 1,000 times a second, and its position is sensed 70,000 times a second. AdOptica, the Italian partnership of Microgate and A.D.S. International that also builds the deformable secondaries of the VLT, has the final design and manufacturing contract, with INAF as subcontractor. Safran Reosc thinned the 12 shells, six plus a spare set, from SCHOTT blanks that start 35 mm thick. The shells are ready for integration at AdOptica, which takes about a year and a half; the unit is then calibrated in a European test tower and shipped to Chile, with completion planned for 2028.
Laser guide stars give the wavefront sensors a reference anywhere in the sky. TOPTICA Photonics of Germany supplied the laser sources and TNO the laser projection subunits. Thales Alenia Space built the adaptive optics wavefront sensing cameras. MORFEO, formerly MAORY, the multi-conjugate adaptive optics relay led by INAF, goes to its Final Design Review in 2026. The maker of the ELT real-time adaptive optics computer hardware is not publicly named.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| M4 adaptive mirror unit, final design and manufacturing | AdOptica (Microgate and A.D.S. International) | Italy | Integrator | In production | 2.4 m, six petals, over 5,000 voice coil actuators; ESO timeline plans completion 2028 |
| M4 adaptive mirror (consortium member) | Microgate | Italy | Manufacturer | In production | Named as AdOptica member in ESO June 2026 contract announcement |
| M4 adaptive mirror (consortium member) | A.D.S. International | Italy | Manufacturer | In production | Named as AdOptica member in ESO June 2026 contract announcement |
| M4 thin shells, polishing, thinning to 1.95 mm and cutting | Safran Reosc | France | Manufacturer | Delivered | 12 shells planned (six plus a spare set); ESO contract marked completed Nov 2023 |
| M4 thin shell glass-ceramic blanks | SCHOTT AG | Germany | Manufacturer | Delivered | Blanks start at 35 mm thick |
| M4 quaternary adaptive mirror (subcontractor) | INAF | Italy | Designer | In production | Listed as subcontractor to AdOptica; specific scope not stated |
| Laser guide star laser sources | TOPTICA Photonics | Germany | Manufacturer | Delivered | ESO contract Dec 2017 to Dec 2022 |
| Laser projection subunits | TNO | Netherlands | Manufacturer | Delivered | ESO contract Dec 2020 to Mar 2025 |
| Adaptive optics wavefront sensing cameras | Thales Alenia Space | France, Italy | Manufacturer | Delivered | ESO contract Dec 2022 to Dec 2024; producing site not stated |
| MORFEO multi-conjugate adaptive optics module, lead institution | INAF | Italy | Designer | In production | Formerly MAORY; Final Design Review in 2026 |
An Italian consortium builds the 80-meter dome and the 3,500-metric-ton structure, ESO's largest contract
The dome is about 80 m high and about 93 m across, a rotating mass of about 6,100 t on 36 trolleys, with slit doors that open 41 m wide. The main structure weighs about 3,500 t today and will pass 4,600 t once the mirrors and instruments are in. Both come from ESO's largest contract, about EUR 400 million, signed in May 2016 with the ACe Consortium of Astaldi and Cimolai, with EIE Group as nominated subcontractor. ESO's contract list now names the members as Cimolai and Webuild, which absorbed Astaldi.
The dome reached its full height with its doors installed in April 2025, the doors first moved later that year, and ESO held the topping-out ceremony in 2025. By July 2026 most of the cladding was on.
ICAFAL of Chile built the road and the summit platform between 2013 and 2017. Abengoa of Spain built the ELT Technical Facility at Paranal in 2018 and 2019. Siemens supplied the 23 kV and 0.4 kV power substations, SAESA of Chile holds the electrical supply contract to November 2049, and Hexagon of Wetzlar supplied the laser trackers used for alignment.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| Dome, about 80 m high and 93 m diameter, 6,100 t rotating mass | ACe Consortium | Italy | Integrator | In production | ESO lists members as Cimolai and WeBuild (successor to Astaldi); EIE Group nominated subcontractor; dome reached full height April 2025 |
| Dome and telescope structure (ACe member) | Cimolai SpA | Italy | Manufacturer | In production | Large steel structures |
| Dome and telescope structure (ACe lead) | Astaldi SpA (now listed by ESO as WeBuild) | Italy | Integrator | In production | ESO 2016 release names Astaldi as ACe member; ESO contract list now names WeBuild |
| Dome and telescope structure (ACe nominated subcontractor) | EIE GROUP | Italy | Designer | In production | ESO names EIE Group as nominated subcontractor to ACe; share of work not stated |
| Telescope main structure, about 3,500 t, first rotation mid 2026 | ACe Consortium | Italy | Integrator | In production | Contract May 2016, about EUR 400 million for dome and structure; ACe is Astaldi and Cimolai with EIE Group as nominated subcontractor |
| Road and summit platform construction | ICAFAL | Chile | Integrator | Delivered | ESO contract Dec 2013 to Feb 2017 marked completed |
| ELT technical facility at Paranal, engineering and construction | Abengoa | Spain | Integrator | Delivered | ESO contract Mar 2018 to Jul 2019 marked completed |
| Power substations (23 kV and 0.4 kV) | Siemens | Germany | Manufacturer | Delivered | ESO contract Oct 2016 to Jul 2018 marked completed |
| Electrical power supply | SAESA | Chile | Operator | In service | Contract runs to Nov 2049 |
| Laser trackers for alignment | Hexagon (Wetzlar) | Germany | Manufacturer | Delivered | ESO contract Oct 2021 to Feb 2025 |
MICADO and METIS will be the first instruments, with Teledyne detectors inside most of them
The first-light instruments are MICADO, an imaging camera led by the Max Planck Institute for Extraterrestrial Physics (MPE); METIS, a mid-infrared imager and spectrograph led by NOVA in the Netherlands; HARMONI, an integral field spectrograph led by STFC in the UK; and MORFEO. In December 2025 MICADO and METIS were in manufacturing, assembly, integration and test, and they will be installed first. HARMONI was rescoped jointly by its consortium and ESO: it now covers 0.75 to 2.4 microns at 12 milliarcseconds, at resolving powers of about 3,000 and 7,000, under new leadership. The second generation, MOSAIC, whose agreement was signed at the end of 2025, and ANDES, is in Phase B.
Teledyne supplied the infrared detectors for HARMONI, MICADO and METIS, CCD220 detectors for MORFEO, MICADO, HARMONI and the PFS-A and PDS stations, and MUSE-type detectors. First Light Imaging of France supplied C-RED cameras for MORFEO. IDOM built the main system of the PFS-A prefocal station, and Bertin of France the powered optics of the phasing and diagnostic station (PDS). AS Scientific Products of the UK supplies the liquid nitrogen infrastructure.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| MICADO first-light imaging camera, lead institution | Max Planck Institute for Extraterrestrial Physics (MPE) | Germany | Designer | In production | In manufacturing, assembly, integration and test as of Dec 2025 |
| METIS mid-infrared imager and spectrograph, lead institution | NOVA | Netherlands | Designer | In production | In manufacturing, assembly, integration and test as of Dec 2025 |
| HARMONI integral field spectrograph, lead institution | STFC | UK | Designer | Planned | Rescoped concept agreed with ESO in 2025; ESO STC feedback due April 2026 |
| Infrared detectors for HARMONI, MICADO and METIS | Teledyne | US | Manufacturer | Delivered | ESO contract Jul 2018 to Jan 2023; Teledyne unit not stated |
| CCD220 detectors for MORFEO, MICADO, HARMONI, PFS-A and PDS | Teledyne | US | Manufacturer | Delivered | ESO contract May 2019 to Jun 2021 marked completed; Teledyne unit not stated |
| MUSE-type detectors | Teledyne | US | Manufacturer | Delivered | ESO contract Sep 2019 to Jun 2021 marked completed |
| C-RED cameras for MORFEO | First Light Imaging (FLI) | France | Manufacturer | Delivered | ESO contract Jul 2018 to Sep 2020 marked completed |
| Prefocal station PFS-A main system | IDOM | Spain | Manufacturer | Delivered | ESO contract Apr 2018 to May 2025 |
| Phasing and diagnostic station (PDS) powered optics | Bertin | France | Manufacturer | Delivered | ESO contract Feb 2023 to Sep 2024 |
| Liquid nitrogen infrastructure | AS Scientific Products Ltd | UK | Manufacturer | In production | ESO contract Nov 2023 to Dec 2026 |
ESO tests machine learning for adaptive optics control on an NVIDIA GPU testbench
Cosylab built the core integration infrastructure for the control software. iTTi and N7 Space of Poland provide central control software engineering through 2027, and Critical Software of Portugal ran independent verification and validation. FEV etamax of Germany supplies dataflow software components under a contract that runs to November 2026.
ESO's GHOST testbench, a real-time computer on NVIDIA GPUs built on the COSMIC platform, tests machine learning for predictive adaptive optics control and contrast control, work that supports the planned ELT Planetary Camera and Spectrograph. The makers of the ELT archive and data center hardware are not publicly named.
| Component | Supplier | Country | Role | Status | Note |
|---|---|---|---|---|---|
| Core integration infrastructure software | Cosylab AB | Sweden | Designer | Delivered | ESO contract Jul 2017 to Jun 2020 marked completed |
| Central Control Software engineering resources | iTTi Sp. z o.o. | Poland | Designer | In production | ESO contract Mar 2023 to Dec 2027 |
| Outsourced central software (CSW) contract | N7 Space Sp. z o.o. | Poland | Designer | In production | ESO contract Mar 2023 to Dec 2027 |
| Independent software verification and validation | Critical Software | Portugal | Designer | Delivered | ESO contract Jan 2016 to Dec 2025 |
| Dataflow software components | FEV etamax GmbH | Germany | Designer | In production | ESO contract Nov 2018 to Nov 2026 |
Cerro Armazones is closed to the public; Paranal next door runs free Saturday tours
The ELT site is not open for public visits. Access needs special authorization from the ELT Site Manager, a helmet, a vest, safety shoes and a signed waiver.
ESO's Paranal Observatory, home of the Very Large Telescope about 20 km away, offers free guided tours every Saturday at 10:00 and 14:00 from the Paranal Visitor Centre, booked only through ESO's online form. The tour does not include the ELT.
Sources
- ESO: the ELT primary mirror (M1)
- Wikipedia: Extremely Large Telescope
- Space.com: the heart of a giant telescope
- ESO: travel to the ELT site
- ESO: ELT timeline
- ESO: ELT industrial contracts
- ESO: ELT status update from the Director General, December 2025
- ESO: largest ELT contract signed for the dome and structure
- UPC: CD6 completes the M1 Local Coherencer optics
- ESO: the ELT secondary and tertiary mirrors
- ESO: the ELT adaptive mirror (M4)
- ESO: the ELT tip-tilt mirror (M5)
- ESO: the ELT dome
- Space.com: the ELT structure rotates for the first time
- ESO: ELT construction progress, July 2026
- ESO: new ELT schedule
- ESO: Annual Report 2025
- Safran: industrial success at ELT scale
- Ideal Investisseur: Safran completes the 931 ELT segments
- ESO: M4 contract announcement, June 2026
- Astrobiology: HARMONI design and science capabilities
- arXiv: the GHOST testbench for machine-learning adaptive optics
- ESO: visiting Paranal
- Pulse: the ELT nears first light
- Inspenet: the ELT mirror segments